Bestway Cement heavily relied on grid and on other energy resources, which led to volatility in operational and productional costs due to increasing energy tariffs.
Bestway installed a 50 MW solar energy project across 4 locations: Farooqia, Kallar Kahar, Chakwal and Hattar and achieved a levelized cost PKR 8/Unit leading to 40% savings vs. on grid.